Images and videos of the Manhattan building analyzed by The Times show that the structural columns buckled directly beneath ...
Why did two load-bearing columns buckle inside a landmark adaptive reuse project? Engineers must stabilize the building ...
Work began Tuesday night to shore up the failed columns on the project converting a commercial office building to apartments, ...
The special inspection agency and a subcontractor are among those under increased scrutiny, even as collapse fears wane.
A major Midtown Manhattan thoroughfare remains gridlocked and seven surrounding buildings have been evacuated after two ...
Realtor.com on MSN
Pfizer Building Developer Says Buckled Columns Were ‘Freak Accident’ Caused by Weight of New Addition
Workers converting the Pfizer Building into a luxury residential tower were forced to evacuate on Tuesday after columns began ...
FOX 5 New York on MSN
Midtown building stable after collapse scare forces mass evacuations
An emergency stabilization effort is underway on Manhattan’s East Side after a 37-story high-rise under construction began ...
A New York Times review of city records shows that the firm, Domani Inspection Services, was repeatedly accused of breaking ...
Buckling columns on a Midtown tower forced evacuations and street closures as city crews investigated the structural failure.
MetroLoft founder Nathan Berman calls the Manhattan high-rise structural damage a "freak accident" limited to a 20-by-20-foot ...
A 37-story high-rise on Manhattan's East Side that sparked fears of a possible collapse has been stabilized, according to ...